Cognor Rolling Mill – Siemianowice Śląskie

The scope of work included comprehensive electrical installations in buildings no. 1, 2, 2A, 2B, 3, 3A, 4. As part of the project implementation, the following tasks were carried out:

  • delivery and installation of LV switchgear,
  • supply and installation of cable trays,
  • supply and installation of low-voltage power cabling,
  • supply and installation of busbar systems for powering cranes,
  • supply and installation of power, control, and socket outlet systems,
  • supply and installation of main, emergency, and evacuation lighting systems,
  • supply and installation of fire protection systems,
  • execution of new grounding, lightning protection, and equipotential bonding installations,
  • post-installation measurements,
  • commissioning of all supplied and installed systems.
Date: