Euroglas Polska Sp. z o.o. Ujazd
Waste heat recovery installation, ORC turbine, Euroglas Polska Sp. z o.o. Ujazd
The scope of work included the electrical implementation of the investment. The following work was performed as part of the implementation:
- modernization of the 15kV MS1-MS2 switchgear: replacement of secondary circuits, retrofitting with Sepam protection;
- delivery and installation of new 0.4kV xEnergy Elite switchboards;
- modernization of existing 0.4 kV switchboards: installation of power circuit breakers in the NSHV 20 switchboard;
- construction of the necessary cable routes for new electrical installations;
- construction of cable canalization for the new building;
- construction of MV, LV and control power supply installations;
- installation of equipotential bonding and grounding of switchboards;
- post-installation measurements